Vertical sides of columns may be be strippted after,
Options
1
1-2 day
Correct Answer
2
7 days
Correct Answer
3
14 days
Correct Answer
4
21 days
Correct Answer
Explanation
Formwork for vertical sides of columns, walls, and beams can be removed relatively quickly, typically after 24-48 hours (1-2 days), as they don't carry significant load.